The short answer
Usually not, in a residential zone. Under the NSW Codes SEPP (cl 2.33–2.34), a fence is exempt development if it's no higher than 1.8 m, with masonry no higher than 1.2 m, and along a road frontage no higher than 1.2 m and at least 20% open above 400 mm. It isn't exempt on a flood control lot, on or beside a heritage item's lot, along a road in a heritage conservation area, or in a foreshore area. Check your council planning certificate before you build.
Fence heights you can build without approval in NSW
For homes in Zones R1–R4 and RU5, which covers most of Maitland's suburbs, an exempt fence must:
- be no higher than 1.8 m above existing ground level, and no more than 1.2 m of it masonry
- along a road frontage or in the front setback, be no higher than 1.2 m and at least 20% open above 400 mm, with solid parts no wider than 350 mm and gaps of at least 25 mm
- on a corner block, follow the front-fence rule for only half the length of the secondary road boundary, measured from the corner
- on a slope, step down so that a 1.8 m fence is no more than 2.2 m high at each step (1.5 m for a 1.2 m fence)
- not have a gate that opens outwards (pool gates are the exception: they open away from the pool)
- if metal, be low-reflective and factory pre-coloured; and not use barbed wire or an electric fence
- on bush fire prone land, be non-combustible or hardwood
Maitland City Council's fences page summarises it the same way: most boundary fences can be built without approval "provided the lot is not identified as subject to flood controls, or heritage restrictions".
Fences on a flood control lot
A fence in a residential zone is not exempt development on a "flood control lot" (cl 2.33(c)), and your council's section 10.7 planning certificate says whether your lot is one. That leaves a complying development certificate, possible only on a part of the lot certified as outside the floodway, flood storage and other high-risk areas and designed not to restrict floodwater, or a development application. Repairing a fence damaged in a natural disaster like-for-like within 2 years can still be exempt (cl 2.30AA–2.30AB). See fences on flood-prone land in Maitland.
The NSW Planning Portal's own summary of the fence rules (last updated 2023) doesn't mention flood control lots, so don't rely on it alone.
Fences in Maitland's heritage conservation areas
The Maitland LEP 2011 has seven heritage conservation areas: Aberglasslyn House, Bolwarra, Central Maitland, East Maitland, Lorn, Morpeth and Regent Street. In them, a fence along a road frontage or in the front setback isn't exempt, and neither is a fence on a heritage item's lot or along its shared boundary, which also affects the neighbours of a heritage item. A side or rear fence behind the building line can still be exempt.
Removing the old fence is a separate question: demolition is never exempt in a heritage conservation area (cl 2.25), so ask council before the old fence comes down; council can confirm in writing that minor work is acceptable (LEP cl 5.10(3)).
For fences that need consent, the Maitland DCP 2026 says front fences in a heritage conservation area "must be no higher than 1.2m in height, unless there is evidence that the original heritage fencing was higher", should be open rather than solid, and should suit the house: timber pickets, low masonry or hedges. Clip-lock and painted steel side fences forward of the building line "are not supported".
Fences on rural and large lots
In rural zones and R5 large-lot residential, an exempt fence must be post and wire or post and rail, no higher than 1.8 m, with no outward-opening gate; on a flood control lot it must not redirect or interrupt the flow of water (cl 2.35–2.36). A Colorbond or paling fence on those lots needs approval. Maitland's DCP adds, for rural dwellings that need consent, that front fences stay under 1.2 m and no more than 50% solid.
Fences on bush fire prone land
An exempt fence on bush fire prone land must be "non-combustible materials or hardwood", so a treated pine paling fence doesn't qualify. The RFS's Planning for Bush Fire Protection 2019 asks for hardwood or non-combustible fences in bush fire prone areas, and non-combustible only within 6 m of a building or at BAL-29 or above. A draft 2026 edition was exhibited in August and September 2026, but the RFS says drafts can't be relied on until it's published.
How to check before you build
- Get the section 10.7 planning certificate for your lot: it shows the zone, flood control lot status, heritage listing and bush fire prone land.
- Check for covenants on your title (an 88B instrument), common in newer estates; they apply whatever the planning rules say.
- On a dividing fence, agree the fence with your neighbour or serve a fencing notice: the Dividing Fences Act applies whether or not approval is needed.
- If any rule above doesn't fit, ask Maitland City Council before building.
Questions about fence height and approval rules
How high can a fence be in NSW without approval?
In residential zones, 1.8 m above existing ground level for side and rear fences, with masonry up to 1.2 m, and 1.2 m along a road frontage (at least 20% open above 400 mm), under the Codes SEPP, if the lot isn't excluded.
Can I build a 2.1 m fence in NSW?
Not as exempt development: the limit is 1.8 m (or up to 2.2 m at each step on sloping ground). A taller fence needs a complying development certificate or a development application, and your neighbour pays only for a sufficient fence.
Does a front fence need council approval in Maitland?
Not if it's no higher than 1.2 m, at least 20% open above 400 mm, and the lot isn't a flood control lot, a heritage item's lot or in a heritage conservation area. In those cases it does.
Does a pool fence need approval?
In residential zones, a fence that forms a pool barrier is exempt if it complies with the Swimming Pools Act (Codes SEPP cl 2.34A–2.34B). Building the pool itself is a separate approval.
Can my fence gate open outwards?
Not on an exempt boundary or front fence: the standard is that a gate must not open outwards. Pool gates are the opposite: they must open away from the pool.
Is a fence on a retaining wall exempt?
Usually not: an exempt retaining wall has to be at least 1 m from each boundary, so a boundary retaining wall needs a complying development certificate or a development application, and it's separate work under a different licence category.
Where this information comes from
The rules and guidance on this page come from these published pages, checked on 28 October 2026.
- State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 · NSW planning policy: cl 1.16, 2.25, 2.30AA–2.30AB, 2.33–2.36, 3.29; read from the version in force from 31 October 2025
- Maitland Local Environmental Plan 2011 · NSW legislation: cl 5.10 (heritage), cl 5.21 (flood planning), Schedule 5 (heritage conservation areas); version in force from 19 September 2025
- Maitland City Council: fences · Council guidance page (read from a 2023 archive copy)
- Maitland DCP 2026, Chapter 4: Heritage · Maitland City Council, in effect 14 April 2026
- Maitland DCP 2026, Chapter 6: Residential Uses · Maitland City Council, in effect 14 April 2026
- Maitland DCP: Hunter River Floodplain (B.3) · Maitland City Council, December 2011 text, part of Maitland DCP 2026 (in effect 14 April 2026)
- NSW RFS: Planning for Bush Fire Protection · NSW Rural Fire Service; PBP 2019 section 7.6 (fences and gates); a draft PBP 2026 was exhibited in August–September 2026 and isn't in force
- NSW Planning Portal: fences (exempt development) · NSW Government, last updated 20 June 2023; doesn't mention the flood control lot or local heritage exclusions